Duke Energy · Stokes County, NC · North Carolina
Early site permit (technology-neutral, six candidate designs) for up to two ~300 MW units next to the Belews Creek coal and gas plant. Duke says it has not yet decided to build.
Power
600 MW
Fission · First commercial
Storage
—
energy capacity
Online
First unit 2036; 600 MW by 2037
approximate target
Capital committed
—
closed or awarded
Capital pending
—
conditional or under review
No project-level financing disclosed yet.
Sources: exchangemonitor.com
Duke Energy (utility-owned)
Utility-owned; Duke hasn't yet decided to build
STEP 4/4 · WATCH Office relaunched as Energy Dominance FinancingLending shifts toward nuclear and utility expansions (AP1000 offers, Constellation uprates).